Hardbrücke restoration, Zurich
The 1,350-metre long structure is used by around 70,000 vehicles per day. The sealing and the pavement have exceeded their life spans, water is permeating the structure. As a result, the structure, which is comprised of six sections (a total of eight exit and entrance ramps), was in dire need of restoration.
The 1,350 m long structure is used by around 70,000 vehicles per day. The sealing and the pavement have exceeded their lifespans, water is permeating the structure. As a result, the structure, which is comprised of six sections (a total of eight exit and entrance ramps), was in dire need of restoration.
Construction method
- New concrete surface, new sealing and new pavement on the road surfaces and ramps
- New road crosswalks and bridge drainage
- New utility line routing
- Local reinforcement measures
- Concrete repair in the hollow bridge elements
- New cantilever plate with guide wall
Map
Zusätzliche Dienstleistungen und Services
Unique features
- Project is coordinated with Zurich-West tram/conversion Pfingstweidstrasse and supporting measures for western bypass
- Extremely complex construction project with a very tight schedule
- Sophisticated, precisely planne construction and transport management
Specific figures
OrganisationProject implementation: joint venture
Construction scheduleJune 2009 - December 2011
Contract valueCHF 70 million